TCN Restores 132kV Owerri-Ahoada Transmission Line After Vandalism-Induced Outage

The Transmission Company of Nigeria (TCN) has restored bulk power supply through its 132kV Owerri-Ahoada Transmission Line following successful reconstruction efforts.

A release signed by its General Manager, Public Affairs, Ndidi Mbah, stated that the line was reconnected to the national grid on April 11, 2025, at approximately 6:00 p.m.

The restoration comes a month after vandals caused the collapse of four transmission towers—towers 71 to 74—on March 11, 2025, leading to power outages in Bayelsa State and parts of Rivers State.

Also Read: Rivers Crisis: Farah Dagogo Drags Tinubu, Akpabio, Abass, Ibas to Court

With the transmission line back in service, the Port Harcourt Electricity Distribution Company (PHEDC) has resumed power supply to the affected areas.

TCN reaffirmed its commitment to delivering reliable electricity nationwide and urged communities to actively support the fight against vandalism of critical infrastructure.

Oh hi there 👋
It’s nice to meet you.

Sign up to receive awesome content in your inbox.

We don’t spam! Read our privacy policy for more info.

More Top Stories

CBN Governance Under Review as Reps Pass Amendment Bill
Rivers Angels Beats Pacesetters Queen
Open Letter to President Donald J. Trump; Hausawa Support for The Abolition of Sharia Laws in Nigeria as a Matter of Religious Freedom and Civil Protection
Edgebase Boosts Cybersecurity Amid Growing AI Threats
FG Bans SS3 Admissions to Curb Exam Malpractice
Onne Port Terminals Invest N167bn in Upgrades

Leave a Reply

Your email address will not be published. Required fields are marked *